GeoEnvironmental & Remediation Services Projects -
Contamination/Environmental
|
|
Client
Givaudan Flavors Corporation
______
Location
Lakeland, Florida
______
Key BCI Staff
Ted Smith, PG, CPG
Ralph Meder
______
Project Costs
$2,500
______
Start Date
May 2007
______
Completion Date
June 2007
|
Water Permit Review & Regulatory/Geologic Assessment
|
|
Scope
BCI's services were obtained by Givaudan Flavors Corporation to perform a water permit review and a regulatory and geologic assessment of their plant in Lakeland, Florida.
The plant consisted of a product warehouse, a processing building, a maintenance storage building, two holding tank farms, and an office building situated on a nine-acre parcel.
BCI staff performed the following tasks:
-
Site inspection
-
Interview with operations personnel
-
Review of current water use permit and available records
-
Sampling and field testing of the recovery and injection water
-
Review of current and historical aerial photographs of the area
-
Research of published local and regional geologic and hydrogeologic data to evaluate the potential for sinkhole development
-
Preparation of a summary report
|
|