h01 Logo Logo h03
BCI Engineers and Scientists
Print E-mail
Water Resources Projects - Dredging

Client
Polk County Board of County Commissioners ______

Location
Polk County, Florida
______

Key BCI Staff
Richard M. Powers, PG, CPG
Walter Reigner, PE, CPESC
______

Project Costs
Construction: $1.5 million
Engineering: $180,000

______

Start Date
1990
______

Completion Date
1992

Banana Lake Feasibility
Study and Restoration

Scope

bananalake-01.jpgThe Banana Lake Feasibility Study and Restoration was the first full lake  restoration project completed in Florida. The project required the assessment of the feasibility of lake restoration and recommendation of restoration means.  Based on the initial engineering study, the decision was made to perform hydraulic dredging restoration.

BCI began by completing surface and groundwater studies to define the potential for adverse impacts. The balance of the restoration project required determination of water circulation and discharge requirements, water quality assurance standards, equipment specification, and design and cost estimates. In addition, laboratory testing, sampling and toxic substance determination was required. To finalize the project, document preparation and agency coordination was required.

Upon completion, one million cubic yards, accounting for 100 percent of the organic muck and silt, was removed and the lake depth was increased by approximately 2.5 feet.

bananalake-02.jpg

 