Water Resources Projects - Ecological

Client
Florida Department of Environmental Protection 
______

Location
Central Florida 
__________

Key BCI Staff
Walter Reigner, PE, CPESC
Mark Schwartz, PE, CFM
Michael Timpe, PE
Scott Wuitschick, PE
Brian Manley
 

______

Project Costs
$1.5 million
______

Start Date
1998
______

Completion Date
Ongoing

Tenoroc Wetland
Mitigation

Scope

tenoroc-01.jpgThis project incorporates an alternative mitigation strategy for wetlands impacted during construction of the Polk Parkway.  Rather than replace impacted wetlands in a disjointed setting, BCI was contracted to replace the wetlands in extensive, adjacent habitats managed for long-term viability and protection. Eighty-seven acres of forested wetlands and thirty-seven acres of herbaceous wetlands will be built in the northernmost sub-basin of the Peace River Watershed. 

The bulk of the mitigation will occur at the  Tenoroc Fish Management Area, a former phosphate mine, to enhance regional outdoor and recreational opportunities. Restoration of the watershed will emphasize improvements in flow and water quality and in the prevention of flooding in downstream areas. Activities completed to date include preparation of a detailed site characterization report, dewatering clay disposal areas, re-routing surface water flows, surface and groundwater quality monitoring and design of the initial wetland mitigation in the North Lake Parker Basin.

 

 tenoroc-02.jpg

 
< Prev   Next >
   
BCI Engineers & Scientists, Inc.  © 2007
Corporate Headquarters : 2000 E. Edgewood Dr., Suite 215, Lakeland, FL 33803 | 877-550-4224