GeoEnvironmental & Remediation Services Projects -
Solid Waste Monitoring
|
|
Client
Zurich North America
______
Location
Monroe County, Michigan
______
Key BCI Staff
Mark Sweatman, CPG
______
Project Costs
$320,000
______
Start Date
May 2001
______
Completion Date
Ongoing
|
Zurich Insurance Site
Assessment and Remediation
|
|
Scope f
In 200f1, BCI completed a site assessment and initial abatement activities to address the release of "free product" unleaded gasoline into the environment. Due toff the initial emergency nature of this work, interaction with federal, state, and local units of government in response to the product release was essential.
BCI addressed impacts to third parties by coordinating the repair of infrastructure, conducting emergency air monitoring, and assessing off-site conditions. Following completion of emergency response actions, fBCI prepared and implemented a corrective action plan and feasibility study of remedial options.
Final system design and a long-term monitoring plan were submitted and approved by the MDEQ. BCI completed the installation of a dual-phase soil vapor extraction system to address free product, soil, and groundwater contamination. BCI completed approximately two years of system operation and monitoring activities.
|
|